Progress being made on CSC Event Center


The new Chicoine Events Center at Chadron State College, part of the $14-million dollar renovation and expansion of the Armstrong Gymnasium Building, is starting to take shape.

Athletic Director Joel Smith says the new arena immediately south of the existing Armstrong Gymnasium has been moving ahead steadily since late spring, but has made great visible progress in recent weeks.

The first two parts of the Armstrong project...conversion of the old swimming pool into a state-of-the-art 6,200-square foot weight room and the old weight room on the gymnasium balcony into the HVAC center for most of the building...have been completed for a couple months.

Smith says the focus is now the Events Center, with crews from prime contractor and construction-manager-at-risk Adolph and Paulson of Colorado and its subcontractors working regular schedules through the holidays, taking off only Christmas and New Year's Day.

Smith says there will a continued burst of visible action immediately after the beams are set in next month, then most of the work for a time will be hidden from the public.

Smith expects new locker rooms to be ready for football and volleyball seasons, although he thinks the volleyball team will probably still play in the current gym...which will be kept as a practice facility after the events center.

The events center is scheduled to be ready for use for basketball next November. It's named for the late Vern Chicoine, a long-time CSC supporter who donated $2.6-million dollars to the project through his estate.

© 2014 Rural Radio Network. All rights reserved. Republishing, rebroadcasting, rewriting, redistributing prohibited. Copyright Information